Multi-Machine CNC Fleet Supply – Central Asia

Project Type:

Factory Expansion – Equipment Supply

Client Type:

General Machinery Parts Supplier

Region

Central Asia

Solution Category

CNC & Precision Manufacturing

Timeline

All 10 machines delivered, installed and accepted within 6 months of contract

Capacity / Scale

50,000+ parts/month after ramp-up

Project Overview

About this project

Case
Multi-Machine CNC Fleet Supply – Central Asia
Description
Ten FEELER machining centres supplied, installed and accepted within six months for a factory expansion — output reached 50,000+ parts/month after ramp-up.
Equipment / Materials Supplied
10 FEELER machining centres — VMP Series VMC (6), VMX Series large-travel VMC (2), NHX-800 HMC (2), all with Fanuc controls
Scale / Capacity
50,000+ parts/month after ramp-up
Timeline
All 10 machines delivered, installed and accepted within 6 months of contract
Project Support Delivered
Factory layout planning · Shipping coordination · Installation supervision · Bilingual applications engineer on site · Russian-language operation and inspection manuals · Four-stage training · Three in-house trainers · Remote diagnostic support

The client’s need

An expanding parts manufacturer could no longer meet its order book: existing machine count and utilisation were not enough. It needed a full batch of new machining centres at once, to build capacity in time for a new delivery window.

Scope of supply

ModelTypeQtyAssigned work
FEELER VMP SeriesVMC6Plates, brackets, flanges and fittings — general milling, drilling and boring
FEELER VMX Series (large travel)VMC2Larger housings and cover parts
FEELER NHX-800HMC2Valve bodies, pump housings and gearbox housings — multi-face machining in one setup
Total 10 

All machines were specified with Fanuc controls, so operators and spare parts are common across the fleet.

Our role

  • Factory layout planning
  • Shipping coordination — main units, tool magazines, electrical cabinets and accessories packed separately for container efficiency
  • Installation supervision: positioning, precision levelling, electrical, pneumatic and coolant connections
  • A bilingual applications engineer on site throughout commissioning
  • Russian-language operation and inspection manuals
  • Four-stage training: daily operation → tool setting and programming → first-level maintenance → independent alarm troubleshooting
  • Three of the client’s staff trained as in-house trainers
  • Remote diagnostic support after handover

Challenges and how we solved them

ChallengeHow we solved it
A fixed six-month window, with compliance work inside itCompliance and documentation were started in parallel with factory production scheduling, not after it, so none of it delayed dispatch.
Long overland transport and a −20 to −30 °C site in winterRail and road transport with border transfer points. Before dispatch, way oil and hydraulic oil were changed to low-temperature grades; machines were nitrogen-purged with desiccant, and spindles and guideways were fixed for transit. Machines arrived and were cleared in stages.
A new building not yet ready for precision machines: foundations, unstable voltage, wet compressed air, no dedicated earthingFoundation drawings (anchor bolt pockets, load, vibration isolation) issued at contract signing, with remote guidance during pouring and curing. Machines levelled with shims on arrival. Voltage stabilisers and isolation transformers supplied; a refrigerated air dryer with three-stage filtration and receiver added; an earthing electrode installed and its resistance measured on site.
Operators new to Fanuc controls, with Russian as the working languageBilingual applications engineer on site, Russian manuals, four-stage training, three in-house trainers, and remote diagnostics to shorten fault response.

Results

  • All 10 machines delivered, installed, commissioned and through first-article acceptance within 6 months of contract — production started on schedule
  • Output reached 50,000+ parts/month after ramp-up
  • The client now runs two shifts with its own operators and first-level maintenance staff
  • Key housing parts are now machined locally, replacing part of the client’s imports
  • The client has discussed a second expansion phase with us

Request a Similar Project Quote

Tell us your project type, target region, and requirements – we will coordinate the right solution and next steps.

Proof of Delivery

Related Project Cases

Other cases in the same solution category.

Middle East
Building Materials Production
Turnkey Production Line Supply

Gypsum Board Production Line – Middle East

A complete turnkey paper-faced gypsum board line for a greenfield investor — from calcination to packed boards. 3,000,000 sq.m/year, delivered within 9 months.
Capacity:
3,000,000 sq.m/year (12 mm board basis)
Timeline:
Delivered within 9 months
Client:
Plant Investor / Greenfield Manufacturer
Middle East
Building Materials Production
Turnkey Production Line Supply (line 1) · Equipment Supply (line 2)

Calcium Silicate Insulation Board Production Line – Middle East

A refractory manufacturer’s first calcium silicate insulation plant — built from zero process know-how, installed through a travel shutdown and brought to stable production remotely. The client has since added a second line and asked us to plan a third.
Capacity:
Single line in regular production at about 3,000 m³/year
Timeline:
Line 1 installed Nov 2019 – Feb 2020; line 2 installed May 2025
Client:
Refractory and insulation materials manufacturer