Middle East

CASE  /

Building Materials Production

Calcium Silicate Insulation Board Production Line – Middle East

Project Type:

Turnkey Production Line Supply (line 1) · Equipment Supply (line 2)

Client Type:

Refractory and insulation materials manufacturer

Region

Middle East

Solution Category

Building Materials Production

Timeline

Line 1 installed Nov 2019 – Feb 2020; line 2 installed May 2025

Capacity / Scale

Single line in regular production at about 3,000 m³/year

Project Overview

About this project

Case
Calcium Silicate Insulation Board Production Line – Middle East
Description
A refractory manufacturer’s first calcium silicate insulation plant — built from zero process know-how, installed through a travel shutdown and brought to stable production remotely. The client has since added a second line and asked us to plan a third.
Equipment / Materials Supplied
Complete calcium silicate insulation board line (line 1); 200 t pipe-section press, 500 t board press, custom moulds and automatic demoulding machine (line 2)
Scale / Capacity
Single line in regular production at about 3,000 m³/year
Timeline
Line 1 installed Nov 2019 – Feb 2020; line 2 installed May 2025
Project Support Delivered
Process and formulation design · Equipment selection · Manufacturing follow-up · Factory inspection · Export documentation and freight · On-site installation guidance (twice) · Live remote support · Commissioning and process optimisation · Ongoing spare parts and process support

The client’s need

A refractory materials manufacturer set out to build its first calcium silicate board line from nothing. It had no process know-how for the product, no equipment, and no capability to manage cross-border delivery and installation itself — it needed one partner from formulation through to a running line.

The site team worked in Arabic, and there would be no resident Chinese technical staff on site. Every problem after start-up would have to be diagnosed and solved from a distance.

Scope of supply

Process: mixing → conveying → reactor → dewatering → hydraulic forming → green-board handling → drying. Curing by autoclaving at 190–200 °C for 6–20 hours, then hot-air drying at 100–180 °C to below 5% moisture.

Temperature grades, process routes, equipment by section and standards for lines like this one are set out on our calcium silicate insulation board and pipe section production line page.

LINE 1 — COMPLETE LINE (2018–2020)

EquipmentQuantity / rating
Mixer1 set, 17 kW
Conveyor1 set, 4.5 kW
Main forming unit (slurry distribution, steam–water separation, air compression)1 set, 21 kW
Steam–water separator1 set
Discharge unit1 set, 3 kW
Hydraulic press1 set
Connecting conveyor1 set
Mould frames300 sets
Trolleys20 sets
Automatic control system1 set

LINE 2 — EXPANSION EQUIPMENT (2023–2025)

EquipmentQuantity
Pipe-section press, 200 t, 1,000 × 1,000 mm platen1
Pipe-section moulds, made to the client’s drawings, with stainless-steel liners16
Board press, 500 t, 1,500 × 1,500 mm platen, with 1,200 × 1,200 mm and 1,200 × 400 mm (×3) moulds1
Automatic demoulding machine with vacuum lifting and PLC control1

PRODUCT AND FORMULATION

Board thickness6–100 mm
Board sizeUp to 600 × 1,200 mm; 1,200 × 1,200 mm with the line 2 press
Density250–300 kg/m³
Compressive strength≥ 0.55 MPa
Flexural strength≥ 0.5 MPa
Service temperature1,050 °C
FormulationCaO : SiO₂ molar ratio 0.95–1.05; fibre 1–8%; mineral additives 0–12%
ReinforcementAlkali-resistant glass fibre, 2–3 cm

Our role

  • Process and formulation design: the full process route, the CaO : SiO₂ formulation system, and autoclaving and drying parameters
  • Equipment selection matched to design capacity; for line 2, the 200 t and 500 t presses and custom moulds for the client’s expansion
  • Manufacturing follow-up with the equipment makers, including the long-lead reactor, hydraulic press and moulds
  • Factory inspection with measured results, and inspection reports before shipment
  • Export documentation including certificate of origin; freight coordination and container loading
  • Installation guidance on site by our engineers, twice: line 1 (November 2019 – February 2020) and line 2 (May 2025, two engineers for press installation and start-up)
  • Live remote support — our process engineers connected with the site team through dedicated messaging groups
  • Commissioning and process optimisation
  • English operation manuals, equipment lists and mould drawings
  • Ongoing spare parts and process support, continuing today

Challenges and how we solved them

ChallengeHow we solved it
Travel stopped in early 2020 — in the middle of installationWe issued an official situation report to the client and moved guidance to live video and messaging the same week. Installation was substantially completed in February 2020, on schedule despite the shutdown.
Steam pressure collapsed whenever both reactors ran at onceDiagnosed remotely as a boiler-capacity limit, not an equipment fault. We reset the reactor operating cycle to match the boiler’s steam output, so both reactors run without pressure loss.
Slurry leaking during pressing because of mould fitPressing time extended from 1 to 5 minutes at a lower pressing speed.
Surface cracks in finished boardsOur process engineers traced the cause to the slurry and reformulated it — adding pulp (dry pulp : water = 1 : 1.5) and adjusting water dosing. Cracking was eliminated in September 2021 and has not returned.
The hot-air flow diagram for the tunnel dryer was missingObtained from the manufacturer’s engineers and passed to the site.
An Arabic-speaking site team with no resident Chinese staffAn interpreter, multilingual messaging groups, and every key parameter confirmed in writing in Chinese and English.

Results

The clearest measure of this project is that the client came back — twice.

  • In production since 2020; every process issue after start-up resolved remotely, with normal production from September 2021; still running steadily in September 2025
  • Regular production at about 3,000 m³/year
  • Second line: contract in October 2023, installed by our engineers in May 2025
  • Third line: in June 2026 the client asked us to plan a new line, including 1,200 × 1,200 mm boards and the plant layout
  • A working relationship since 2018 — eight years and three lines

Request a Similar Project Quote

Tell us your project type, target region, and requirements – we will coordinate the right solution and next steps.

Proof of Delivery

Related Project Cases

Other cases in the same solution category.

Middle East
Building Materials Production
Turnkey Production Line Supply

Gypsum Board Production Line – Middle East

A complete turnkey paper-faced gypsum board line for a greenfield investor — from calcination to packed boards. 3,000,000 sq.m/year, delivered within 9 months.
Capacity:
3,000,000 sq.m/year (12 mm board basis)
Timeline:
Delivered within 9 months
Client:
Plant Investor / Greenfield Manufacturer
Scroll to Top